Oakridge Court

180 units · $42.6M TIV · Permanent conversion 11/15

Construction to permanent

The handoff nobody owns

Continuous coverage from builder's risk through occupancy, substantial completion and permanent loan conversion. Target conversion Nov 15, 2026.

  1. 01

    90–60 days

    Confirm the dates

    • Confirm occupancy and conversion dates
    • Update values, entities and permanent underwriting
    • Refresh the TIV and business-income worksheet
  2. 02

    60–30 days

    Resolve structure

    • Resolve CAT, flood, deductible and clause items
    • Quote permanent coverage
    • Circulate exception packages still open
  3. 03

    Before occupancy

    Consent and responsibility

    • Obtain builder's-risk carrier consent
    • Document insurance responsibility during partial occupancy
    • Confirm contractor coverage remains in force
  4. 04

    At conversion

    Bind and evidence

    • Coordinate permanent binding
    • Issue evidence to lender, investor and HFA
    • Review builder's-risk cancellation timing
  5. 05

    Post-close

    Deliver and calendar

    • Deliver final policies and endorsements
    • Track renewal evidence and ongoing covenants
    • Hand the record to servicing